Ebla Gas Facility
Discipline: Front-End EngineeringClient: Petro-Canada (Palmyra) BV
Location: Central Syria
Front End Engineering Design of gas gathering system, pipelines and gas treatment/LPG extraction plant. Design, tendering & award of long lead packages. Preparation of ITT package for subsequent EPCC.
The ode Scope of Work consisted of project management & project control services, all engineering from the wellheads via the gas gathering station and gas treatment plant through to export, including all hydrocarbon carrying/ produced water injection (1x4", 5km) and raw water pipelines (2x4", 5km).
The total man-hours for the FEED scope was 70,500 hours.
The work entailed:
- process selections & design of gas facilities, including LPG extraction, by either refrigeration, or turbo-expander process
- flow assurance design of well flowlines and pipeline, which included line size selection and slug catcher sizing & configuration
- materials selection for all facilities & equipment
- site selection of GGS/GTP and route selection for flowlines & pipeline
- All plant layouts and infrastructure & amenities and construction requirements
- civil buildings & preparatory works design
- mechanical, electrical, instrumentation & control and telecommunications design of complete plant & systems
- full HSE scope; including HAZID, HAZOP & SIL analysis.
- preparation of long lead item requisitions and ITT packages, tendering, evaluation & completion of purchase orders
- Preparation of EPCC tender package for full field development through to start-up & hand-over
General design premise:
- gas production 80 MMscfd (DCQ), peak 96 MMscfd
- max. oil production 640 m3/d (4000 bbl/d)
- max. total production (oil and water) 720 m3/d (4530 bbl/d)
- max. water production 400 m3/d (2515 bbl/d)